IT TOOK 37 MONTHS TO TRANSFORM A LAND...
MR. S. GOENKA ON INAUGURATION CEREMONY- 26 NOVEMBER’ 2014
INAUGURATION CEREMONY- 26 NOVEMBER’ 2014
INAUGURATION CEREMONY- 26 NOVEMBER’ 2014
INAUGURATION CEREMONY- 26 NOVEMBER’ 2014
2015- COAL HANDLING PLANT STARTS OPERATION IN FULL SWING
28TH JANUARY- 2015- FIRST UNIT STARTS COMMERCIAL OPERATION
28TH MARCH 2014- FIRST LIGHT UP OF BOILER
2013- 400 KV SWITCHYARD ERECTION
2013- INTAKE PUMP HOUSE CONSTRUCTION
2013- STACKER CUM RECLAIMER ERECTION BEGINS
2013- COAL CONVEYOR STRUCTURE CONSTRUCTION IN PROGRESS
TURBINE- GENERATOR PUT IN PLACE
2013- TURBINE DECK CASTING
2013- ELECTRO STATIC PRECIPITATORS
2012- 400 KV SWITCHYARD PEDESTAL ERECTION STARTED
2012- COOLING TOWER CONSTRUCTION STARTS
2012- ASH HANDLING PLANT FOUNDATION STARTS
2012- TRACK HOPPER CONSTRUCTION IN PROGRESS
2012- CHIMNEY RAFT CASTING
2012- BOILER AND POWER HOUSE BUILDING FOUNDATIONS
2012- CONSTRUCTION OF ADMIN BUILDING