HEL CONSTRUCTION HISTORY
Tower construction

Tower construction

IT TOOK 37 MONTHS TO TRANSFORM A LAND...

MR. S. GOENKA ON INAUGURATION CEREMONY- 26 NOVEMBER’ 2014

INAUGURATION CEREMONY- 26 NOVEMBER’ 2014

INAUGURATION CEREMONY- 26 NOVEMBER’ 2014

INAUGURATION CEREMONY- 26 NOVEMBER’ 2014

2015- COAL HANDLING PLANT STARTS OPERATION IN FULL SWING

28TH JANUARY- 2015- FIRST UNIT STARTS COMMERCIAL OPERATION

28TH MARCH 2014- FIRST LIGHT UP OF BOILER

2013- 400 KV SWITCHYARD ERECTION

2013- INTAKE PUMP HOUSE CONSTRUCTION

2013- STACKER CUM RECLAIMER ERECTION BEGINS

2013- COAL CONVEYOR STRUCTURE CONSTRUCTION IN PROGRESS

TURBINE- GENERATOR PUT IN PLACE

2013- TURBINE DECK CASTING

2013- ELECTRO STATIC PRECIPITATORS

2012- 400 KV SWITCHYARD PEDESTAL ERECTION STARTED

2012- COOLING TOWER CONSTRUCTION STARTS

2012- ASH HANDLING PLANT FOUNDATION STARTS

2012- TRACK HOPPER CONSTRUCTION IN PROGRESS

2012- CHIMNEY RAFT CASTING

2012- BOILER AND POWER HOUSE BUILDING FOUNDATIONS

2012- CONSTRUCTION OF ADMIN BUILDING

Field Inspection

Project Site in 2008

Cooling Tower PVD installation

Areal Over View BTG

HEL Green Field